HANGZHOU, Dec. 1 (Xinhua) -- An 843-megawatt gas turbine was officially connected to the grid on late Sunday in east China's Zhejiang Province, after completing a 168-hour full-load trial run.
The unit, the first of two at the China Energy Investment Corporation Co., Ltd. plant in Anji County, achieves a remarkable efficiency rate of 64.15 percent, representing an approximately 17-percentage-point increase over conventional million-kilowatt coal-fired units.
Shen Chengliang, a manager at Huzhou branch of the State Grid Zhejiang Electric Power Co., Ltd., said that the turbine units, once fully operational, will generate up to 7 billion kWh of electricity annually, sufficient for the power supply of 6 million residents, strengthening the local power grid with low-carbon electricity.
Low-carbon power generation is a key driver of China's strategy to meet its dual carbon goals -- to peak carbon emissions by 2030 and achieve carbon neutrality by 2060. ■